It takes 10 days for digging a trench of 100 m long, 50 m broad and 10 m deep. What length of trench, 25 m broad and 15 m deep can be dug in 30 days ?

 It takes 10 days for digging a trench of 100 m long, 50 m broad and 10 m deep.  What length of trench, 25 m broad and 15 m deep can be dug in 30 days ?

      a) 400 m          b) 200 m          c) 100 m          d) 89m
























Expl : More days, more length (Direct)

      Less breadth, more length (Indirect)

      More depth, less length (Indirect

      Days      10 : 30;

      Breadth  25 : 50;                  : : 100 : x

      Depth    15 : 10;              



      :. 10 * 25* 15 * x = 30 *50 * 10 *100

            x= (30*50*10*100)/10*25*15 = 400

     So the required length = 400m

Comments

Popular posts from this blog

The telephone bill of a certain establishment is party fixed and partly varies as the number of calls consumed. When in a certain month 540 calls made the bill is Rs.1800. In another month 620 calls are consumed then the bill becomes Rs.2040. In another month 500 units are consumed due to more holidays. The bill for that month would be :

 The telephone bill of a certain establishment is party fixed and partly varies as the number of calls      consumed. When in a certain month 540 calls made the bill is Rs.1800. In another month 620 calls are      consumed then the bill becomes Rs.2040. In another month 500 units are consumed due to more      holidays. The bill for that month would be : a) Rs.1560           b) Rs.1680      c) 1840            d) Rs.1950  Expl : Let the fixed amount be Rs. X and the cost of each unit be Rs. Y.     Then, 540y + x = 1800 …. And 620y + x =  2040     On subtracting (i) from (ii), we get 80y = 240 -> y = 3     Putting y = 3 in (i) we get :     540 * 3 +  x = 1800 x = (1800-1620) = 180     . :  Fixed charges = Rs.180, Charge per unit = Rs.3.     Total charges for consuming 500 units = 180 +(500*3) = Rs.1680