6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in - days.

 6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in - days.

A. 4 days

B. 6 days

C. 2 days

D. 8 days



Let work done by 1 man in 1 day = m and work done by 1 woman in 1 day = b 

Work done by 6 men and 8 women in 1 day = 1/10 

=> 6m + 8b = 1/10

=> 60m + 80b = 1 --- (1)

Work done by 26 men and 48 women in 1 day = 1/2 

=> 26m + 48b = ½

=> 52m + 96b = 1--- (2)

Solving equation 1 and equation 2. We get m = 1/100 and b = 1/200

Work done by 15 men and 20 women in 1 day 

= 15/100 + 20/200 =1/4

=> Time taken by 15 men and 20 women in doing the work = 4 days

Comments

Popular posts from this blog

Find the number of perfect squares in the given series 2013, 2020, 2027,.

Find the number of perfect squares in the given series 2013, 2020, 2027,................, 2300   (Hint 44^2=1936) a. 1   b. 2    c. 3   d. Can’t be determined Answer: a Explanation: The given series is an AP with common difference of 7. So the terms in the above series are in the form of 2013 + 7k.  We have to find the perfect squares in this format in the given series. Given that 44^2 = 1936. Shortcut: To find the next perfect square, add 45th odd number to 44^2. So 45^2 = 1936 + (2 x 45 -1) = 2025 46^2 = 2025 + (2 x 46 - 1) = 2116 47^2 = 2116 + (2 x 47 - 1) = 2209 Now subtract 2013 from the above numbers and divide by 7. Only 2209 is in the format of 2013 + 7k.  One number satisfies.

It takes 10 days for digging a trench of 100 m long, 50 m broad and 10 m deep. What length of trench, 25 m broad and 15 m deep can be dug in 30 days ?

 It takes 10 days for digging a trench of 100 m long, 50 m broad and 10 m deep.  What length of trench, 25 m broad and 15 m deep can be dug in 30 days ?       a) 400 m          b) 200 m          c) 100 m          d) 89m Expl : More days, more length (Direct)       Less breadth, more length (Indirect)       More depth, less length (Indirect       Days      10 : 30;       Breadth  25 : 50;                  : : 100 : x       Depth    15 : 10;                     :. 10 * 25* 15 * x = 30 *50 * 10 *100             x= (30*50*10*100)/10*25*15 = 400      So the required length = 400m