6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in - days.

 6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in - days.

A. 4 days

B. 6 days

C. 2 days

D. 8 days



Let work done by 1 man in 1 day = m and work done by 1 woman in 1 day = b 

Work done by 6 men and 8 women in 1 day = 1/10 

=> 6m + 8b = 1/10

=> 60m + 80b = 1 --- (1)

Work done by 26 men and 48 women in 1 day = 1/2 

=> 26m + 48b = ½

=> 52m + 96b = 1--- (2)

Solving equation 1 and equation 2. We get m = 1/100 and b = 1/200

Work done by 15 men and 20 women in 1 day 

= 15/100 + 20/200 =1/4

=> Time taken by 15 men and 20 women in doing the work = 4 days

Comments

Popular posts from this blog

It takes 10 days for digging a trench of 100 m long, 50 m broad and 10 m deep. What length of trench, 25 m broad and 15 m deep can be dug in 30 days ?

 It takes 10 days for digging a trench of 100 m long, 50 m broad and 10 m deep.  What length of trench, 25 m broad and 15 m deep can be dug in 30 days ?       a) 400 m          b) 200 m          c) 100 m          d) 89m Expl : More days, more length (Direct)       Less breadth, more length (Indirect)       More depth, less length (Indirect       Days      10 : 30;       Breadth  25 : 50;                  : : 100 : x       Depth    15 : 10;                     :. 10 * 25* 15 * x = 30 *50 * 10 *100             x= (30*50*10*100)/10*25*15 = 400      So the required length = 400m