It was calculated that 75 men could complete a piece of work in 20 days

It was calculated that 75 men could complete a piece of work in 20 days. When work was scheduled to commence, it was found necessary to send 25 men to another project. How much longer will it take to complete the work?





















Answer: 30 days. 
Explanation: Before: One day work = 1 / 20 
One man’s one day work = 1 / ( 20 * 75) 
Now: No. Of workers = 50 
One day work = 50 * 1 / ( 20 * 75)
 The total no. of days required to complete the work = (75 * 20) / 50 = 30

Comments

Popular posts from this blog

Find the number of perfect squares in the given series 2013, 2020, 2027,.

Find the number of perfect squares in the given series 2013, 2020, 2027,................, 2300   (Hint 44^2=1936) a. 1   b. 2    c. 3   d. Can’t be determined Answer: a Explanation: The given series is an AP with common difference of 7. So the terms in the above series are in the form of 2013 + 7k.  We have to find the perfect squares in this format in the given series. Given that 44^2 = 1936. Shortcut: To find the next perfect square, add 45th odd number to 44^2. So 45^2 = 1936 + (2 x 45 -1) = 2025 46^2 = 2025 + (2 x 46 - 1) = 2116 47^2 = 2116 + (2 x 47 - 1) = 2209 Now subtract 2013 from the above numbers and divide by 7. Only 2209 is in the format of 2013 + 7k.  One number satisfies.