A piece of work can finish by a certain number of men in 100 days. If however, there were 10 men less, it would take 10 days more for the work to be finished. How many men were there originally?

A piece of work can finish by a certain number of men in 100 days. If  however, there were 10 men less, it would take 10 days more for the work to be finished. How many men were there originally?

            a)75                 b)82                 c)100               d)110

























 Expl: Originally let there be x men.

      Less men, more days (Indirect)

      :. (x-10): x : : 100 :110 or x-10/x = 100/110

     or 11x-110 = 10x or x =110

     So, originally there were 110 men.

Comments

Popular posts from this blog

It takes 10 days for digging a trench of 100 m long, 50 m broad and 10 m deep. What length of trench, 25 m broad and 15 m deep can be dug in 30 days ?

 It takes 10 days for digging a trench of 100 m long, 50 m broad and 10 m deep.  What length of trench, 25 m broad and 15 m deep can be dug in 30 days ?       a) 400 m          b) 200 m          c) 100 m          d) 89m Expl : More days, more length (Direct)       Less breadth, more length (Indirect)       More depth, less length (Indirect       Days      10 : 30;       Breadth  25 : 50;                  : : 100 : x       Depth    15 : 10;                     :. 10 * 25* 15 * x = 30 *50 * 10 *100             x= (30*50*10*100)/10*25*15 = 400      So the required length = 400m