A piece of work can finish by a certain number of men in 100 days. If however, there were 10 men less, it would take 10 days more for the work to be finished. How many men were there originally?

A piece of work can finish by a certain number of men in 100 days. If  however, there were 10 men less, it would take 10 days more for the work to be finished. How many men were there originally?

            a)75                 b)82                 c)100               d)110

























 Expl: Originally let there be x men.

      Less men, more days (Indirect)

      :. (x-10): x : : 100 :110 or x-10/x = 100/110

     or 11x-110 = 10x or x =110

     So, originally there were 110 men.

Comments

Popular posts from this blog

The telephone bill of a certain establishment is party fixed and partly varies as the number of calls consumed. When in a certain month 540 calls made the bill is Rs.1800. In another month 620 calls are consumed then the bill becomes Rs.2040. In another month 500 units are consumed due to more holidays. The bill for that month would be :

 The telephone bill of a certain establishment is party fixed and partly varies as the number of calls      consumed. When in a certain month 540 calls made the bill is Rs.1800. In another month 620 calls are      consumed then the bill becomes Rs.2040. In another month 500 units are consumed due to more      holidays. The bill for that month would be : a) Rs.1560           b) Rs.1680      c) 1840            d) Rs.1950  Expl : Let the fixed amount be Rs. X and the cost of each unit be Rs. Y.     Then, 540y + x = 1800 …. And 620y + x =  2040     On subtracting (i) from (ii), we get 80y = 240 -> y = 3     Putting y = 3 in (i) we get :     540 * 3 +  x = 1800 x = (1800-1620) = 180     . :  Fixed charges = Rs.180, Charge per unit = Rs.3.     Total charges for consuming 500 units = 180 +(500*3) = Rs.1680